DDA Published a Notification for Delay in Possession Pockets D2 & D3 Sector-29

DDA

Delhi Development Authority (DDA) has published a notification for the allottees of Pockets D2 & D3 of Sector-29 (as per the list enclosed) are hereby informed that earlier these plots could be handed over due to being coming under the existing Prahladpur Khera Khurd Road. A water-line of 300mm diameter is running along this road for feeding water to the adjoining villages like Barwala, Prahladpur etc.

An alternative new water-line has been approved so that the old road may be abandoned and plots may be released. This whole exercise of Removal and replacement of water-line from these plots is likely to be completed by the end of May 2016 and these plots would be available for taking over possession from 1st week of June 2016.

Here is  the published notification by Delhi Development Authority: Click Here